EVM Calculator

Calculate earned value management metrics including CV, SV, CPI, SPI, EAC, ETC, and VAC with this free EVM Calculator for project managers.

936.3K uses Updated · 2026-05-06 Runs locally · zero upload
AD

How to Use the EVM Calculator

The EVM Calculator gives project managers an instant view of project health through earned value metrics.

  1. Enter BAC — Budget at Completion: the total approved budget for the project.
  2. Enter PV — Planned Value: how much work should have been done by now, in budget terms.
  3. Enter EV — Earned Value: the budgeted value of work actually completed.
  4. Enter AC — Actual Cost: the real money spent to achieve the earned value.
  5. Read Results — The EVM Calculator computes CV, SV, CPI, SPI, EAC, ETC, and VAC with color-coded indicators.

Formula & Theory — EVM Calculator

The core formula or rule set used by the EVM Calculator is summarized in the table below:

MetricFormulaGood Value
CV (Cost Variance)EV − ACPositive
SV (Schedule Variance)EV − PVPositive
CPI (Cost Performance Index)EV ÷ AC> 1.0
SPI (Schedule Performance Index)EV ÷ PV> 1.0
EAC (Estimate at Completion)BAC ÷ CPILower is better
ETC (Estimate to Complete)EAC − AC
VAC (Variance at Completion)BAC − EACPositive

Use Cases for the EVM Calculator

  • Project Status Reviews — Present EVM metrics to stakeholders in weekly or monthly project reviews using the EVM Calculator.
  • Budget Forecasting — Use EAC and ETC to update project cost forecasts based on current performance trends.
  • Schedule Recovery Planning — Identify schedule slippage early with SV and SPI to trigger corrective actions.
  • PMP Exam Practice — Use the EVM Calculator to verify your manual calculations when studying for the PMP certification.
  • Multi-project Portfolio Management — Compare CPI and SPI across multiple projects to prioritize management attention.

Frequently asked questions about EVM Calculator

What is Earned Value Management (EVM)?

EVM is a project management technique that integrates scope, schedule, and cost to objectively measure project performance and forecast future outcomes.

What does CPI less than 1 mean?

A CPI below 1.0 means the project is over budget — you are spending more than the value of work completed. The EVM Calculator color-codes metrics to make this immediately visible.

How is EAC calculated?

The EVM Calculator uses the formula EAC = BAC ÷ CPI, which assumes future work will be performed at the same cost efficiency as work completed so far.

What is the difference between ETC and EAC?

EAC (Estimate at Completion) is the forecasted total project cost. ETC (Estimate to Complete) is only the remaining cost from the current point to completion. ETC = EAC − AC.